Qtectic and the State have agreed on State-funded modifications for the DSAPT Works which are passed through to Alstom on a back-to-back basis.
Accessibility Variation Project
Qtectic and the State have agreed on State-funded modifications for the DSAPT Works, which are passed through to Alstom on a back-to-back basis.
Overview:
- The State, Qtectic and Alstom have negotiated the terms of a Rebaselining and DSAPT Amendment Deed (RDAD).
- The scope of works is to modify the current Multiple Units (MUs) by installing a new toilet module including specific design features developed through consultation with Disability Access PWG. Making the MU’s compliant with the Disability Standards for Accessible Public Transport 2002.
- The DSAPT Works modifications are being carried out by the DSAPT Sub-contractor (Downer EDI) at their facility in Maryborough.
- Downer EDI will act as sub-contractors to the DSAPT Contractor (Alstom) who will in turn be directly subcontracted by Qtectic under a DSAPT Works Contract.
Organisational structure for Delivery of the DSAPT works